Filters
·
Performance Overview
KPI Summary
OEE
-
eUPS %
-
MSA %
-
⏸ Planned Stops %
-
🛑 Unplanned Stops %
-
+
🐢 Speed Loss / Unexplained %
-
+
♻ Waste & Rework %
-
Capacity & Reliability
Capacity Utilization
Time Base CU%
-
Volume Base CU%
-
Asset Productivity Index (API)
-
Equipment Reliability
MTBF (hrs)
-
MTBS (hrs)
-
MTTR (hrs)
-
Minor Stops /100h
-
Trends
OEE Trend
| Period | OEE | eUPS % | Planned Stops | Unplanned Stops | Waste & Rework |
|---|
Capacity Breakdown per Category
| Category | Hours | % of capacity | By group |
|---|
Capacity in Cases per Line & Material
| Line | Material | UoM | Good Production | Planned Stoppages | Not Occupied | Unplanned Stoppages | Speed Loss / Unexplained | Waste & Rework | Total Capacity |
|---|
Stoppage, speed-loss, waste and good-production cases come from logged hours at each product's nominal speed. Not Occupied cases are the line's unscheduled hours (available − occupied) at the nominal speed of the products it ran, shared by occupied time.
Loss Analysis
Top Stoppage Reasons (Pareto)
·Loss Contribution by Line (eUPS %)
Capacity Lost by Line (Cases)
Operational Detail
Stoppages by Line & Machine
The shaded Line Total row carries Speed Loss & Waste & Rework (calculated per run, not per machine).
| Line | Machine | Events | Total Min | Planned | Unplanned | Speed Loss / Unexplained | Waste&Rework (min) | Waste Qty (units) |
|---|
Run Log
| Date | Line | Shift | Material | Planned Qty (Cases) | Actual Qty (Cases) | Waste&Rework Qty (Bottles) | OEE % | MSA % |
|---|